Chapter 15. Claims Arising from Employment Relations (Sections 2178-2240)
16.06.2022.
Judgment of the Department of Civil Cases, case No SKC-128/2022
Inadmissibility of amending or supplementing the notice of appeal after the expiry of the time-limit for its submission; Time for examination of goods and notification for lack of conformity in accordance with the United Nations Convention on Contracts for the International Sale of Goods
12.10.2021.
Judgment of the Department of Civil Cases, case No SKC-9/2021
Quality assurance of construction works in case of insolvability of the builder
14.09.2021.
Judgment of the Department of Civil Cases, case No SKC-3/2021 (CHANGE OF CASE-LAW)
Retention amount as an object not recoverable in insolvency proceedings; Unfair denial to satisfy a claim due to a formal breach of the time limit for the claims of creditors (CHANGE OF CASE-LAW)
30.09.2020.
Judgment of the Department of Civil Cases, case No SKC-1027/2020
Reasonable doubts of the debtor as the basis for release from the adverse consequences of delay
18.06.2020.
Judgment of the Department of Civil Cases, case No SKC-492/2020
Separation of one-off performance with intermediate payment from periodic performance
05.05.2020.
Judgment of the Department of Civil Cases, case No SKC-59/2020
Recovery of losses arising from termination of a contract entered into in a public procurement procedure
26.06.2019.
Judgment of the Department of Civil Cases, case No SKC-166/2019
Some aspects of consideration of a dispute arising from a contract for work-performance
11.10.2018.
Judgment of the Department of Civil Cases, case No SKC-215/2018
Objection with regard to non-performance of a contract against an action for performance of a bilateral contract
29.09.2017.
Judgment of the Department of Civil Cases, case No SKC-209/2017
Reasonable doubts of the creditor as reason for default of the performance of obligation
31.10.2016.
Judgement of the Department of Civil Cases, case No SKC-340/2016
Duty to pay when accepting an order performed according to a contract for work-performance; duty of the court to facilitate settlement between the parties in the course of the court procedure
30.10.2015.
Judgement of the Department of Civil Cases, case No. SKC-229/2015
Issues regarding application of the Convention for the International Carriage of Goods by Road
16.10.2015.
Judgement of the Department of Civil Cases, case No SKC-112/2015
Recovery of contractual penalty for delay, if performance is accepted after the performance deadline stipulated in the contract
25.01.2012.
Judgement of the Department of Civil Cases of the Senate, case No SKC-227/2012
Segregation of personal character of sustenance contract from execution of liabilities stated in the contract
18.04.2012.
Judgement of the Department of Civil Cases of the Senate, case No SKC-126/2012
Substantiation of cancellation of contract due to loss of interest
29.03.2000.
Judgment of the Department of Civil Cases, case No SKC-127/2000
Damages resulting from unilateral termination of the employment agreement. The severance pay shall be included in the amount to be recovered for the period of compulsory leave
26.11.1997.
Judgment of the Department of Civil Cases, case No SKC-440/1997
The employer is exempted from compensation only if it is proved that the cause of the mutilation is a gross violation of labor protection rules and instructions by an employee himself
12.11.1997.
Judgment of the Department of Civil Cases, case No SKC-416/1997
Compensation in case both parties acted wrongfully depends on the degree of the fault, depending on whether the act was committed with wrongful intent or only due to negligence – various degrees of fault according to the article 1640 of the Civil Law
03.09.1997.
Judgment of the Department of Civil Cases, case No SKC-277/1997
Compensation of the damage caused by failure to save the goods under transportation
09.04.1997.
Judgment of the Department of Civil Cases, case No SKC-86/1997
In the event of the debtor's default, the obligation does not end in itself and remains in force
26.02.1997.
Judgment of the Department of Civil Cases, case No SKC-15/1997
The liability of the employer if the employee has caused losses while performing his or her duties